Future Energy 06 Aug 2026

Latest look inside Louisiana LNG

Louisiana LNG continues to gather momentum, with the project on the US Gulf Coast now 28 per cent complete as we work towards first LNG cargo in 2029.

Since announcing a final investment decision more than 14 months ago, activities at the site have ramped up. Two massive LNG storage tanks and three LNG trains are under construction, with the project remaining on budget.

(See for yourself what’s been achieved with a drone’s-eye view below.)

Located in Calcasieu Parish, Louisiana, between Houston and New Orleans, the Louisiana LNG project constitutes a US$17.5 billion investment.

Its strategic location provides access to abundant, low-cost US natural gas, strengthening our ability to deliver secure, reliable energy to our customers.

Structural steel has now been erected for both Trains 1 and 2, while concrete pilings progressed for Train 3.

At the end of Q2, Trains 1, 2 and 3 were 35 per cent, 25 per cent and 18 per cent complete, respectively.

The two large LNG storage tanks are also taking shape. Once complete, they are set to be the biggest in North America, each holding 235,000 m3 – more than 90 Olympic-sized swimming pools.

Other highlights include dredging Berth 1 to the required depth to allow for the LNG carriers to access the terminal, as well as commencing roof panel installation on Tank 1.

The benefits of the project reach beyond our fenceline. The recent services contract award to Louisiana-based supplier Green Tug Towing for the design and construction of four new tugboats, is just one example of Woodside and its contractors’ commitment to engaging local suppliers.

Next up?

The growing Louisiana LNG team remains focused on safely delivering the project. Priorities include progressing construction of the three LNG trains, advancing the LNG jetty and completing the walls of the storage tanks ahead of roof installation.