Facility maintenance information

Our operated facilities are renowned for their safety, reliability and efficiency.

Planned annual maintenance campaigns play an important role in our base business, and support our vision to bring new resources through proven LNG facilities. 

2026 maintenance key dates

Information in this table regarding scheduled maintenance shutdowns is:

  • supplied pursuant to Australian Competition and Consumer Commission Authorisation No AA1000620-1 (Authorisation);
  • provided in good faith and published as a condition of the Authorisation; and
  • based on Woodside’s reasonable expectations and is subject to change.
Facility Scope Approximate start date Approximate end date

Pluto LNG Park

One LNG Train

1 May 2026

4 June 2026

Karratha Gas Plant

One LNG Train

4 September 2026

3 October 2026